Compare What Each Storage Project Quote Actually Includes

KIMBARRY brings design, supplier selection, custom manufacture, specialist works, commissioning and continuing service into one project quotation. The scope, inclusions, acceptance requirements and contractual commitments can be checked together.

Wine cellar planning table with floor plans, material samples, paper, and writing tools.
Design concept

Use one consistent project brief

Prepare a dated collection inventory and site brief for every bidder. Include the intended use, storage quantities, packaging dimensions, room measurements, available drawings, construction stage and relevant photographs.

Record unresolved information explicitly. A provisional allowance or an unconfirmed site condition should not be treated as an established inclusion.

  • Collection inventory and intended use.
  • Site dimensions and architectural drawings.
  • Construction stage and available utilities.
  • Unresolved assumptions and provisional items.
  • Date and revision of the project brief.

Separate the work into comparable categories

Ask each supplier to identify the exact products, services and interfaces included in its proposal. Distinguish a cabinet or equipment supply from custom cabinetry and a coordinated whole-room project.

A lower quotation does not necessarily represent better value if it excludes work included in another proposal.

  • Detailed design and coordination.
  • Custom cabinetry and storage racks.
  • Enclosure, doors and glazing.
  • Environmental equipment and controls.
  • Electrical and other site interfaces.
  • Packing, transport and delivery.
  • Installation and commissioning.
  • Operating instructions and maintenance.

Define commissioning and acceptance in advance

Agree the inspection items and acceptance process before work begins. Specify measurement locations, testing periods, loading conditions, door-opening conditions and the records that will be provided.

Identify who is responsible for correcting deficiencies and what happens if the agreed acceptance conditions are not met. Do not rely on an undefined promise that the room will perform as expected.

  • Inspection checklist and measurement positions.
  • Test period and operating conditions.
  • Required monitoring and commissioning records.
  • Corrective-work responsibility.
  • Written acceptance criteria.

Handover and continuing service

KIMBARRY brings design, supplier selection, custom manufacture, specialist works, commissioning and continuing service into one project quotation. The scope, inclusions, acceptance requirements and contractual commitments can be checked together.

KIMBARRY remains the single point of contact for agreed maintenance, fault handling and later adjustments. Operating information and service arrangements are included in the handover.

KIMBARRY defines the project responsibilities, checks and handover requirements clearly. Warranty periods, response times, acceptance criteria and continuing services are agreed in each project contract.